Cable Pulling · Watford, Hertfordshire

33kV Cable Pull & Jointing — Industrial Estate, Watford

Three drum lengths of 33kV triplex through a live industrial estate, pulled and jointed inside a four-day shutdown window.

LocationWatford, Hertfordshire
DateJune 2025
Voltage33kV
Scale600m / 3 joints
ClientICP (Independent Connection Provider)

When the developer of a new logistics park north of Watford was given a four-day shutdown window by the DNO to bring 33kV power onto the site, the ICP responsible called us in to handle the pulling and jointing element. The site sat off a Hertfordshire A-road, with the connecting switchgear inside a live primary substation half a mile away.

Three drum lengths of 240mm² triplex 33kV XLPE had to be pulled through pre-laid duct, with two straight joints and one termination at the new packaged substation. Tight bend radii on the substation approach, plus a 90° change of direction at the road crossing, made tension control critical.

What the job involved

  • Pre-pull duct rodding and mandrel test on all three duct runs (approx. 600m total).
  • Three drum-to-drum pulls of 240mm² 33kV XLPE triplex, tension-monitored with live data logging.
  • Two straight joints in pre-cast pit boxes at the road crossing and field boundary.
  • Outdoor termination at the new 33/11kV packaged substation, plus indoor terminations at the existing primary.
  • VLF and partial discharge testing handed over to the DNO at end of works.

Key challenges

  • Substation access window of just 14 hours per day, restricting jointing pit lighting setup.
  • One run had a flooded pit that needed pumping out and damming before jointing could start.
  • Drum positioning had to thread around an existing 11kV overhead line — no crane swings within the exclusion zone.

Outcome

  • Pulls completed within calculated tension envelope (max recorded 8.2kN against a 12kN design max).
  • All three joints passed VLF and PD testing first time.
  • Site handed back to the DNO half a day inside the shutdown window — letting the ICP complete commissioning early.

Tight window, live site, and they didn't miss a beat. The pull data logs and joint records landed in my inbox before we'd even cleared the site.

— ICP Project Manager, Watford, Hertfordshire